Total installed capacity 18 MW or over
Total design capacity 35 MW or over

List of Main Past Projects


Shitara, Aichi: 899.14 kW


Ise, Mie: 471.20 kW


Iwata, Shizuoka: 298.90 kW


Acquired by
Environmental Energy Division
<
Location Capacity Power sales start time Remarks
Hamamatsu, Shizuoka 568.96kW 2019, September  
Shitara, Aichi 899.14kW 2019, August
Fukuroi, Shizuoka 85.80kW 2019, June  
Fukuroi, Shizuoka46.08kW 2019, June  
Toyokawa, Aichi 279.00kW 2019, April  
Toyokawa, Aichi 282.10kW 2019, March  
Hamamatsu, Shizuoka 48.00kW 2019, March  
Hamamatsu, Shizuoka 82.08kW 2019, February  
Iwata, Shizuoka 298.90kW 2019, February  
Ina, Nagano 1,761.76kW 2018, December  
Toyokawa, Aichi 738.72kW 2018, March  
Tahara, Aichi 1,324.80kW 2017, March  
Kosai, Shizuoka 291.20kW 2017, January  
Iwata, Shizuoka 52.00kW 2016, October  
Kosai, Shizuoka 1,578.96kW 2016, June  
Kosai, Shizuoka 2,212.00kW 2016, April  
Ise, Mie 471.20kW 2015, July